LBP Codewords

Complaints not upheld

Codewords #122

24 January 2025

5 minutes to read

Recent ‘not upheld’ decisions on complaints to the Building Practitioners Board show that professionalism, good record keeping, and open communication with clients do not simply make good business sense...

The Building Practitioners Board considers complaints against LBPs. To assist the Board, the Registrar of LBPs delegates the task to the Investigations Team within Occupational Regulation, MBIE. The Registrar will provide a report to the Board for consideration. If the Board decides to hold a hearing and an LBP has breached a ground for discipline, the complaint is upheld and the Board will then decide on an appropriate penalty. 

If sufficient evidence is not obtained the complaint may be ‘not upheld’ by the Board.

Recent ‘not upheld’ decisions show that professionalism, good record keeping, and open communication with the client are not simply good business sense, they can also provide evidence in response to potential complaints. 

In one of those ‘not upheld’ decisions, the respondent was contracted to build an extension on a 1950s holiday home. The build was delayed at the framing stage by weather events and insurance claims related to Cyclone Gabrielle. 

The Board decided to investigate whether the respondent had, contrary to section 317 of the Act: 

  • carried out or supervised building work in a negligent or incompetent manner 

  • carried out or supervised work that does not comply with a building consent 

  • failed to provide a record of work (RoW) 

  • breached the Code of Ethics, and 

  • conducted himself in a manner that brings, or is likely to bring, the regime into disrepute. 

Regarding the Code of Ethics allegations, the specific points were: 

  • You must comply with the law 

  • You must price work fairly and reasonably and 

  • You must conduct your business in a methodical and responsible manner 

The specific Code of Ethics matters under investigation related to the absence of a building contract (Provision 10) and his contract administration processes (Provisions 21 and 25) 

The Board’s findings: 

Negligence or Incompetence 

The complainant commissioned a report from a building consultant after a commercial dispute following the weather event. The report was to work out what stage the job was at. 

The consultant’s report raised compliance issues, including, among others, that there had been no inspection of the piles and foundations, and that the flooring was installed without following the manufacturer’s instructions. The respondent provided evidence that the building consent authority had issued a waiver for that inspection because there was engineer oversight. The respondent explained that the flooring was installed in that way so the machinery could get to the retaining wall that was being built. This would also allow the framing work to continue. 

The Board noted that, while not everything was up to acceptable standards, the respondent did not act in a negligent or incompetent manner. 

Contrary to a Building Consent 

Building consents provide detailed plans and specifications for building work and are issued on the understanding that the building work will meet the provisions of the Building Code. 

The early designs submitted for a building consent included the engineering design of the retaining wall, however, during the RFI process, the designer omitted the retaining wall design in favour of battering the slope. A subsequent change to on-site conditions meant that battering would not be sufficient, so the respondent asked for input from the designer and the engineers, and construction of the retaining wall carried on. 

The Board decided that there was not any building work that was different from the building consent. 

Failure to Provide a Record of Work  

An LBP must provide a record of work when they complete their restricted building work. 

The building work stopped because of contractual issues. The respondent provided evidence that they were attempting to return and continue the work, and there was no formal contractual termination. The respondent said the first they heard they would not be continuing was when they received the complaint, and because of this, the Board found that work was complete when the complaint was made. 

As the complaint was made before the work was complete, the respondent had not committed the disciplinary offence of failing to provide a RoW. 

Code of Ethics and Disrepute 

The high threshold test applied to negligent or incompetent conduct also applies to Code of Ethics breaches and disreputable conduct, in that the conduct must be sufficiently serious enough for the Board to make a disciplinary finding. 

The respondent provided copies of a contract and disclosure information for the project during submissions prior to the hearing. The complainant accepted that they had been provided with those documents so the Board will not investigate the allegation further. 

Regarding the respondent’s contract administration processes, the issue under investigation was whether the respondent dealt with cost fluctuations and variations in the correct way. Again, the respondent provided the Board with copies of correspondence with the complainant which showed that they were following a process and communicating with the complainant regarding those items. The Board decided that further investigation was not necessary. 

The outcome 

The Board decided not to uphold the complaint as the respondent did not commit a disciplinary offence. 

Record your Codewords articles relevant to your licence class and complete the quiz for your LBP skills maintenance requirements. 

Share
Related articles